R & B DIVISION

INTRODUCTION

"Connectivity is the lifeline for development of a nation". Public Works Department (PWD) with its wings  ( Roads & Buildings) serves the very purpose for development of our country since its inception. In our district, PWD9R& B) was born as a sub-division during 1952 and subsequently converted to a division during 1974 for looking after construction & maintenance of Roads , Bridges & Buildings of the entire Rayagada Revenue District. At present it is functioning effectively with its 5 sub-divisions & 17 sections at different places of Rayagada District

This division maintains total 589.7 Km of road consisting of SH, MDR, & ODR. It also maintains 48  Major bridges and minor bridges & 918  residential & non residential buildings in the entire district.

This division has got the distinction of extending its sincere service and participation to address to the problems at district level and has been working in coordination with other Departments to achieve the common goals of district administration from the day of its formation.

ACTIVITIES & PROJECT SCHEMES

1. ROAD SECTOR

This Division has constructed the following roads which are passing through the thickly populated tribal villages thereby improved the socio-economic condition of the trial people.

a. Kuli A.P. Boarder Road :

This road has been constructed at an estimated cost of Rs.98.00 lakhs during 1992 with much difficulty on Ghat portion which links to Andhra Pradesh.

b. Kashipur-Gunupur Road:

This road has been constructed at an estimated cost of Rs.237.19 Lakhs out of IFAD Grant which reduced the distance from Kasipur to Kalahandi District.

c.Kashipur-ThuamulRampur:

This road has been constructed at an estimated cost of Rs.307.97 lakhs out of NABARD assistance which links to Thuamul Rampur Block of Kalahandi District.

During the last ten years this Division has maintained all the roads under its jurisdiction in a most efficient manner as per funds available time to time

2. BRIDGE SECTOR

This Division has constructed a number of prestigious bridges efficiently , some of which are illustrated below:

A. HL Bridge over Bansadhara near Gunupur on SH-4:

This bridge has been completed in the year 1994 and inaugurated by the Hon'ble the than Chief Minister Sri Biju Patnaik on 17.5.94

On completion of the bridge the distance of Rayagada to Gajapati Dist. has been reduced by 18 KM and fulfilled the long -outstanding demand of people of Gunupur. The details of the bridg

(i) Span  2 X 37.5 m 9 X 50.9 m
(ii) Estimated cost  9.99 crores
(iii) Period of completion  2 years

       The construction of Road over Bridge at Rayagada is a land mark achievement of this Division. It is an important ROB constructed in Orissa during 1992 in record time.

It fulfilled the long -outstanding demand of the people of Rayagada by providing uninterrupted traffic to Andhrapradesh and Chatishgarh from Rayagada District. The details of ROB is as below:

(i) Span 41 nos.(total length 451. m)
(ii) Estimated cost  4.91 crores
(iii) Period of completion  2 years

C. In addition to the above , the following important bridges have been constructed during the last 10 years which provided all weather traffic to Koraput district, Andhrapradesh and Chatishgarh. Thereby the entire picture of industrially developed Rayagada District has been changed during the past 10 years.

On Koraput - Laxmipur - Rayagada - Gunupur Road : (S.H - 4) :

(i) Punjapai bridge          58.25 lakhs
(ii) Kumbhikota bridge                       35.75 lakhs
(iii) Pichudi bridge                        65.43 lakhs
(iv) Talagumma bridge                  22.31 lakhs
(v) Gumma bridge                        23.48 lakhs

(vi) Chattisghat - I               

        61.87 lakhs

(vii) Chattisghar - II             

        100.88 lakhs

(viii) Sankesh - II                  

        194.321 lakhs

(ix) Japakhal                         

        203.830 lakhs

(x) Sankesh I                    

        158.690 lakhs  

On Rayagada - Kereda Road (MDR 48 B):

(i) Parsulgeda bridge 114.00 lakhs

(ii) Ottigeda bridge 

67.50 lakhs

(iii) Ladda bridge 

49.91 lakhs

On Kashipur- Gunupur Road :

(i) Adatikiri bridge 29.56 lakhs

(ii) Bribaphula bridge

21.60 lakhs

(iii)Sunger birdge

37.86 lakhs

On Kashipur - Thuamul Rampur Road :

(i)  Petafulla  bridge 51.60 lakhs

On Komtalpeta - Klayansinghpur Road ( S.H. 45) :

(i) Laxmipur bridge 36.00 lakhs

(ii) Kasuguda bridge

58.07lakhs
(iii) Pettiguda bridge 50.69 lakhs

(iv) Dhamalima bridge

35.96 lakhs

3.BUILDING SECTOR

This division has pioneered in construction of a number of prestigious buildings in addition to maintaining all Residential & Non-residential buildings of Rayagada District.

(i) CJM Court building at Rayagada

: Rs.41.20 lakhs

(ii) D.I.C. building at Rayagada

: Rs.14.69 lakhs

(iii) Seed Testing Laboratory at Rayagada

: Rs.32.47 lakhs

(iv) Local Office & Staff Quarters of ESI Corporation at J.K.Pur

: Rs.15.92 lakhs

(v) Collectors Residence at Rayagada

: Rs.22.31 lakhs

(vi) Fire Station Building at Rayagada & Gunupur

: Rs.32.34 lakhs

(vii) Police barrack at Rayagada

: Rs.15.00 lakhs

(viii) Educational Complex at Kurli

: Rs.13.00 lakhs

(ix) Educational Complex at Puttasing

: Rs.13.00 lakhs

At present the following Six nos. important Building are being taken up and in progress

(i) Collectorate Building    

: Rs. 30.00 lakhs

(ii) Circuit House at Rayagada             

: Rs. 19.76 lakhs

(iii) DIET Institution Building:    

: Rs.48.16 lakhs

(iv) Construction of 50 seated Boys hostel for DIET at Bissamcuttack :

: Rs. 40.65 lakhs

(v) Construction of Staff Qtrs for DIET at Bissamcuttack :        

: Rs. 18.09 lakhs

(vi) Construction of 40 seated Girls Hostel for DIET at Bissamcuttack :

: Rs. 36.58 lakhs

Apart from the above building, this division has constructed a number of Government buildings like R.I. Office cum Residence, Health Department Buildings at remote and inaccessible areas of Rayagada District.

PROJECTS TARGETS & ACHIEVEMENTS

Sl.No

Name of the project

Estimated Cost (In Lakhs)

Date starting the work

Likely date of completion

Physical progress

Financial progress

Remarks

During the F.N.

Cumulative

During the F.N.(In Lakhs)

Cumulative ( In Lakhs)

1

C.R.F. WORKS

Construction of H.L. bridge over Dhamalima nallaha at 22nd K.M. of K.K.S. Road(S.H.-45)

35.958

15.5.02

14.4.03

Completed

Completed

0.5

23.50

 -

2

Construction of HL bridge over Kasiguda nallaha at 34th K.M. of K.K.S. Road ( S.H-45)

58.07

17.6.02

16.5.03

Completed

Completed

4.5

37.00

-

3.

Improvement to road from 2/0 to 8/0 K/M/ & 1/6 to 2/o K.M. of Rayagada-Kereda road(MDR 48B)

75.00

5.6.02

4.5.03

Completed

Completed

0.5

5.55

-

4

NABARD WORKS

Improvement to Th.Rampur Kashipur road from 13/150 to 40/150 K.M. ( R.I.D.F.III) Ph.II

307.976

28.3.00

31.3.03

BT - 200 m

Metalling work completed & BT work 60% completed

--

218.00

Work in progress

5

Constn. of H.L. Bridge over Japakhal at 100/6-8 km of K.L.R. road9SH-4) of Koraput-Laxmipur-Rayagada-Gunupur Road ( SH-4)

203.83

01.12.02

31.05.04

Completed

--

--

--

The work allotted to M/sO.B.C.C. ltd by Work Dept. Work Started

6

Construction of H.L. bridge over Sankesh Nallah I at 99/6-8 K.M of K.L.R.G. Road ( S.H-4)

158.69

01.02.03

Work stopped due to non approval of Rates by Tender Committee

Left abutment completed up to cap level, Right abutment completed up to 2.0 Mt above bed level.

--

--

--

Work awarded to OBCC

7

I.F.A.D. WORKS- Construction of H.L. bridge over Tujer nallah at 21st K.M. of Surugunja - Manasgam road ( Balance work)

40.40

--

--

--

--

--

--

Tender for balance work to be invited afterapproval of revised GAD

8

PLAN SCHEME - Construction of H.L. bridge over Ottigedda nallah at 23/800 K.M. of Rayagada- Kereda Road(M.D.R.-48B)

67.50

6.6.01

31.3.03

Completed

Completed

--

--

 

9

Construction of H.L. bridge over Petigedda nallaha at 30/4-6. K.m. of K.K.S Road(SH-45)

50.68

12.12.02

11.11.03

Progress

Progress

--

--

Work in Porgress.

10

KBK Works - Improvement of Ramnaguda-B.Cuttack road from 28/0 to 29/450 KM

10.00

15/11/02

14/2/03

Completed

Completed

--

-

Completed

11

Improvement such as Regradation of Kailash kota Ghat from 132/8 to 133/2 KM of K.L.R.G.Road(SH-4)

10.00

4/12/02

3/3/03

Completed

Completed

--

--

Completed

12

Improvement of Bhabanipatna-Muniguda Road from 56/0 to 57/0 KM & 63/0 to 63/5 KM

10.00

31/12/02

30/3/03

Completed

Completed

--

--

Completed

13

Imporivement to Komtalpeta-Muniguda_tumudibandha Road from 20/150 to 20/900 KM & 34/250 to 35/0 km

10.00

31/12/02

30/3./03

Completed

Completed

--

--

Completed

14

Improvement to Rayagada Kerada Road(MDR 48 B) from 21/600 to 23/0 KM

10.00

4/12/02

3/3/03

Completed

Completed

--

--

Completed

15

Improvement to B.Cuttack-Gumuda road 15/6 to 17/2 KM

10.00

15/11/02

14/2/03

Completed

Completed

--

--

Completed

16 a.

Construction of H.L. bridge over Sankesh nallah II at 99/4-6 KM of K.L.R.G. Road ( SH-4)

159.24

01.02.02

01.05.04

Completed

Completed

--

--

Completed

 b.

Improvement to Komtalpeta - Kalyansinghpur road (SH-45) (under KBK)

50.00

23..3.03

22.09.03

Completed

--

--

--

Completed

 c.

Improvement to Rayagada -Kerada Road (MDR 48B) (0/450-1/400 & 16/200-21/600km) ( under KBK)

50.00

21.02.03

20.08.03-

Completed

--

--

--

Completed

 d.

 

Improvement to Bissamcuttack-Muniguda- Bhawanipatna Road(SH-6) 9 from 40/5-48/0 & 57/0-65/5 km) (under KBK)

50.00

05.03.03

04.09.03

Completed

--

--

--

Completed

e.

Improvement to Koraput Laxmipur Rayagada- Gunupur from 78/0-110/0 in streches

50.00

10.05.03

09.11.03

MT-4.00 Km BT-4.00 Km completed

--

--

--

Work in progress, ( MT-1.08 Km, BT-1.08 Km to eb done)

17

Construction of H.L. bridge over Gate nallah on Komtalpeta Muniguda- Tumudibandha Road  SH- 5 at 37/0 Km

99.99

--

--

--

--

--

--

Tender in process, Agreement to be drawn

 18

Construction of H.L. bridge over Jigidi  nallah on Bhawanipatna Muniguda- Road   SH- 6 at  45 /2 KM

198.68

--

--

--

--

--

--

A/A Awaited

19

Improvement of Bissamcuttack-Muniguda- Bhawanipatna Road from 61/950-62/300 & 67/165-67/800 km) (

25.00

27.11.03

26.05.04

MT-0.90 Km BT-0.90 Km E/W- 0.665 Km Sub-base 0.665 Km completed

--

--

--

Balance work in progress

20

 

Improvement of Ramanaguda Bissamcuttack  Road(SH-6) 9 from 1/0-1/500 & 4/0-4/500 Km, 21/0-22/0 & 25/0 25/800 KM

30.00

27.11.03

26.05.04

MT- 1.41 Km. BT-1.41 Km completed

--

--

--

Balance work in progress

21

Improvement of Koraput Laxmipur Rayagada- Gunupur from 113/0-113/310, 156/560-156/980 & 170/0 to 171/0, 175/8 176/100 Km

25.00

27.11.03

26.05.04

MT-1.63  Km BT-1.32 Km completed

--

--

--

Balance work in progress)

22

 

Improvement of Komtalpeta Muniguda- Tumudibandha Road(SH-5) from 9/300 to 10/200, 18/0 20/0 Km

25.00

25.02.04

24.04.04

BT-0.52Km completed

--

--

--

Balance work in progress

23

Improvement of Gunupur _ Padmapur Road ( MDR) from 5/0 6/74 Km

20.00

19.11.03

18.05.04

MT-1.74  Km completed

--

--

--

Balance work in progress

24

Improvement of Rayagada- Kereda Road ( MDR- 48 B ) from 13/300 15.840 Km

30.00

27.11.03

26.05.04

MT-1.54  Km BT-1.70 Km   completed-

--

--

--

Balance work in progress

25

Improvement to Culverts and road of Bhawanipatna Gunupur Kashipur Rupkona Road ( SH-44) from 96/200-96/850, 112/0 113/ 0 Kn & Cd work at 117/970 Km

20.00

23.01.04

22.0304

MT-1.54  Km BT-1.54 Km   CD 1 No completed

--

--

--

Work completed

26

 Building Works

Construction of Collectorate Building atRayagada  ( Right Wing)

30.00

26.09.02

25.08.03

Completed up to Lintel level

--

--

--

Work in progress

27

Construction of Institution Building of DIET at Bissamcuttack

48.157

15.05.02

14.02.03

Brick work in super structure in progress

--

--

--

Work in progress

28

Construction of 50 seated Boys Hostel  Building of DIET at Bissamcuttack

40.651

29.04.02

28.03.03

Brick work in super structure in progress

--

--

--

Work in progress

29

Construction of 1 D-Type, 1 E-Type staff quarters fro DIETat Bissamcuttack

18.089

20.06.02

19.12.02

Brick work in super structure in progress

--

--

--

Work in progress

30

Construction of Circuit House at Rayagada

19.76

25.02.04

24.01.05

Foundation completed

--

--

--

Work in progress

31

Construction of  Girls Hostel building  for DIET Institution at Bissamcuttack

36.58

28.02.04

27.08.04

Work just started

--

--

--

Work in progress

32

Construction of 4 nos. E type quarters ( Ph-1) for staff of civil judge ( Sr. & Jr. Division ) at Gunupur under RLTAP ( KBK)

15.05

28.02.04

27.01.05

Foundation completed

--

--

--

Work in progress

33

Construction of 2 nos of F type quarters ( Ph-1) for staff of civil Judge ( Sr. & Jr. Division )m at Gunupur under RLTAP ( KBK)

6.96

28.02.04

27.11.04

Foundation completed

--

--

--

Work in progress